REFERENCESBelarus / 2022Completed

Bychow Belarus

Biomass CHP plant for a pellet production site

Explore the plantTechnical data
BelarusProject year 2022Commissioning 2022

The biomass CHP plant in Bychow supplies a pellet production site and feeds 80 million kWh of electricity into the grid every year.

43.26 MW

Thermal input

46 t/h

Steam output

max. 12 MW

Electrical output

Challenge

Untreated biomass and residues from the company's own production serve as fuel. Flue gas cleaning had to meet the limits under Belarusian law; the state environmental impact assessment was passed in December 2019.

Sectional drawing with boiler, electrostatic precipitator and stack in Bychow
Technical drawing from the Kablitz project description

Solution

Kablitz supplied the plant from the walking floor to the stack: fuel feeding, reciprocating grate firing and boiler for 46 t/h at 85 bar and 495 °C, turbine with air-cooled condenser, electrostatic precipitator and flue gas condenser.

Result

Since 2022, the plant has generated 80 million kWh of electricity and 144 million kWh of heat every year. The flue gas condenser lowers the flue gas temperature to 75–95 °C.

Technology

Technology

Bychow, Belarus

Fuel
Biomass and production residues
Firing system
Reciprocating grate
Thermal input
43.26 MW
Boiler output
38.5 MW
Steam output
46 t/h
Live steam
85 bar (a) / 495 °C
Electrical output
max. 12 MW
Heat output
max. 18 MW
Flue gas cleaning
Electrostatic precipitator, flue gas condenser
Commissioning
2022